- Creating estimate and plan with agile -Concepts and techniques for developing valuable software
Knowledge about the target uncertainty product What to make
Uncertainty of means Knowledge about the project How to make it
Closely related to new [Knowledge Acquisition
Three typical
Technical and Business Risks
You're talking about cost-effectiveness, net present value, internal rate of return, etc., but you can't estimate enough to make that argument in many cases.
star shell
Do not divide the story into tasks
The source of this term seems to be "master programmer."
Don't separate "implement the UI" from "implement the middle tier."
Implement across all, even partially, rather than completing only one specific logic layer
why?
Parkinson's Law The amount of work expands until all the time given for completion is met
Schedule delays are transmitted ahead of time.
Clark and Wheelwright's experiment with multitasking More than three tasks at the same time reduces productivity.